ILLUSTRATIVE SAMPLE · 22 OCT 2026
Reference campus.
A conditional decision.
An example of an early screening format. Synthetic data, with no real site, verified supply or completed project.
IT LOAD24 MW
ASSUMED PUE1.25
TOTAL DEMAND*30 MW
IT PHASES2 × 12
*24 × 1.25 = 30 MW as an initial approximation. This does not include a capacity reservation or grant.
CONDITIONAL / ILLUSTRATIVE CONCLUSION
Confirm an access and connection route compatible with the load and resolve the planning status before the next land or engineering commitment.
1. Hard-gate matrix
| GATE | HYPOTHESIS | OUTSTANDING EVIDENCE | ASSESSMENT |
|---|---|---|---|
| Power | Demand in two phases | Specific access and connection documents | To be confirmed |
| Land and permits | Compatible parcel | Land control and planning checks | Conditional |
| Cooling and water | Buyer configuration | Design, availability and permits | To be defined |
| Fibre and resilience | Two conceptual routes | Carrier confirmation and route diversity | Conditional |
| Schedule | Phased sequence | Grid, permit and construction milestones | Dependent |
2. Conditions before progressing
- Define the demand hypothesis with the buyer: MW IT, PUE, redundancy, cooling, phases and COD.
- Distinguish published, requested and granted capacity. Obtain specific evidence for the connection point.
- Cross-check land control, compatible use and the authorisation sequence.
- Confirm connectivity and cooling requirements with providers and specialists.
- Rebuild the schedule around documented milestones, assigning an owner to each dependency.
3. Evidence register
| DATA / CLAIM | SOURCE / ISSUER | DATE / VERSION | STATUS / LIMIT ON USE |
|---|---|---|---|
| Power capacity | To be completed | To be completed | Not available in this sample |
| Parcel control | To be completed | To be completed | Not available in this sample |
| Planning compatibility | To be completed | To be completed | Not available in this sample |
4. Next decision
Review the dossier when sufficient evidence becomes available. The result may change to Advance, remain Conditional or move to Stop / Redesign.